Two bridges on Narayangadh – Muglin road section brought into service

Bharatpur, Nov 30 : Two new bridges have been brought into service along the Narayangadh-Muglin road section.  


A bridge each constructed over the Lamo Baluwa and Dumre rivulets on this road section have been opened for vehicular traffic since Wednesday, said Bijaya Darai, an engineer of the Nagdhunga-Muglin Road Project Western Sector (Narayangadh-Muglin).   

 
He said five bridges have already been brought into service before this on the Narayangadh-Muglin road section. Among the 19 bridges under construction on the road section, these five bridges have been constructed in the first phase.    


Engineer Darai said that the bridge over the Seti Dobhan rivulet has already been put into service before this. Similarly, preparations have been made to bring into service by Friday the bridges at Topekhola and Chisenji as well.    


According to him, works have been expedited to bring eight among the remaining under-construction bridges into use within two months.

A bridge each is under construction at Jugedi, Simaltal, Riddhi, Bhorle, Namsi, Tope, Kalikhola and Khahare on the Narayangadh-Mugling road section. He added that construction of a bridge each over the Khahare II and Tuinkhola rivulets will take more time.  (RSS)

  • Nepal News Agenacy Pvt. Ltd.

  • Putalisadak, Kathmandu Nepal

  • 01-4011122, 01-4011124

  • [email protected]

  • Department of Information and Broadcasting Regd.No. 2001।077–078

©2024 Nepal Page | Website by appharu.com

Our Team

Editorial Board